This is not the current EPA website. To navigate to the current EPA website, please go to www.epa.gov. This website is historical material reflecting the EPA website as it existed on January 19, 2021. This website is no longer updated and links to external websites and some internal pages may not work. More information »

When conducting an asbestos abatement operation that is not a small-scale, short-duration project, what amount of asbestos-containing material triggers the requirement to use Asbestos Model Accreditation Plan-accredited workers?

Response actions other than a small-scale, short-duration project must be designed and conducted by Asbestos Model Accreditation Plan (MAP)-accredited persons. See 40 CFR part 763.90(g). Additionally, the asbestos National Emission Standards for Hazardous Air Pollutants (NESHAP), Occupational Safety and Health Administration (OSHA), state and local training requirements may apply.