This is not the current EPA website. To navigate to the current EPA website, please go to www.epa.gov. This website is historical material reflecting the EPA website as it existed on January 19, 2021. This website is no longer updated and links to external websites and some internal pages may not work. More information »

Response to Request for AIS Waiver for Ductile Iron Flanges for Mobile, Alabama

EPA did not approve this waiver request. 

EPA found two manufacturers that could supply the AIS-compliant products that met the Mobile Area Water and Sewer System (MAWSS) project specifications and could be delivered on time to avoid significant delays in the project schedule for the CC Williams Wastewater Treatment Plant Headworks and Primary Clarifier projects. The applicant confirmed the domestic products were suitable.