This is not the current EPA website. To navigate to the current EPA website, please go to www.epa.gov. This website is historical material reflecting the EPA website as it existed on January 19, 2021. This website is no longer updated and links to external websites and some internal pages may not work. More information »

Enbridge Spill August 2010 Work Plans Submitted

Work plans submitted by Enbridge in 2010 and EPA Notices approving or disapproving them.

The components of the work plan are:
  1. Health and Safety Plan
  2. Pipeline Repair workplan
  3. Sampling and Analysis Plan
  4. Quality Assurance Project Plan (QAPP)
  5. Oil Containment and Recovery Plan
  6. Source Release Area Remediation Plan (SAR)
  7. Remediation Plan for Downstream Impacted Areas (RPDIA)
  8. Waste Treatment, Transportation and Disposal Plan

See also Final Approved Enbridge Work Plans - August 2010