This is not the current EPA website. To navigate to the current EPA website, please go to www.epa.gov. This website is historical material reflecting the EPA website as it existed on January 19, 2021. This website is no longer updated and links to external websites and some internal pages may not work. More information »

Fuels Registration, Reporting, and Compliance Help

The regulations state that a party must register three months prior to producing or importing gasoline or blendstocks under the RFG and anti-dumping Program (40 CFR 80.76). If a party receives its ID numbers from EPA prior to the end of the three month pe

The party does not need to wait. The three month period was intended to give EPA adequate time to process registrations. A party may proceed with production and importation after receiving an EPA registration number.(1/30/95)

This question and answer was originally posted at Consolidated List of Reformulated Gasoline and Anti-Dumping Questions and Answers: July 1, 1994 through November 10, 1997 (PDF)(333 pp, 18.17 MB, EPA420-R-03-009, July 2003, About PDF)