If the applicant has a personnel management system with adequate internal controls, EPA will base its review of requested personnel costs on the previous application request. Costs within 10% of the previous application
request will be deemed necessary and reasonable. Applicants must explain variations greater than 10% in their narrative, or in a separate, written format. POs should provide notations as to where the applicant’s explanation may be found.
Cost review template and guidance for project officers grants Under 40 CFR Part 35 Subpart A
You may need a PDF reader to view some of the files on this page. See EPA’s About PDF page to learn more.