This is not the current EPA website. To navigate to the current EPA website, please go to www.epa.gov. This website is historical material reflecting the EPA website as it existed on January 19, 2021. This website is no longer updated and links to external websites and some internal pages may not work. More information »

Dusable Park Photo Gallery

Photo gallery for Lindsay Light- Dusable Park

July 2020

Future DuSable Park seeding project aerial viewView from the Flyover of the completed seeding project at Future DuSable Park.

Northeast view of Future DuSable Park completed seeding projectView from the northeast corner of the Future DuSable Park completed seeding project.

Future DuSable Park completed seeding project southeast viewView from the southeast corner of the Future DuSable Park completed seeding project.

June 2020

New topsoil delivered to DuSable ParkNew topsoil delivered to DuSable Park.

View of completed sheet pile wall capsView of completed sheet pile wall caps.

View of completed sheet pile wall caps 2Another view of completed sheet pile wall caps.

View of DuSable Park with completed sheet pile wallView of DuSable Park with completed sheet pile wall.

April 2020

East wall of DuSable Park

Contractors install perimeter wall and barrier, referred to as a fender.

DuSable Park work

Closeup view of the newly installed barrier, also known as a fender.

Tie rod installation along East wall of DuSable Park

DuSable Park wall retaining wall detail.

View of North wall of DuSable Park

DuSable Park wall retaining wall detail.

February 2020

Contractors install perimeter wall and barrier, referred to as a fender

Contractors install perimeter wall and barrier, referred to as a fender.

Closeup view of the newly installed barrier, also known as a fender.

Closeup view of the newly installed barrier, also known as a fender.

Chicago Park District contractor installing pile caps along Southeast corner of new seawall.jpgChicago Park District contractor installing pile caps along Southeast corner of new seawall

Chicago Park District contractor installing pile caps along Southeast corner of new seawall.

Dusable wall retaining wall detail

DuSable Park wall retaining wall detail.

January 2020

Chicago Park District contractors install new seawall along the northeast corner of DuSable Park.
Chicago Park District contractors install new seawall along the northeast corner of DuSable Park.
New seawall installation along the northwest corner of DuSable Park
New seawall installation along the northwest corner of DuSable Park
Chicago Park District contractors excavate and screen soil for thorium contamination at southern boundary of DuSable Park.
Chicago Park District contractors excavate and screen soil for thorium contamination at southern boundary of DuSable Park.
View of excavation along southwest corner of DuSable Park.
View of excavation along southwest corner of DuSable Park.
Chicago Park District contractors install sheet pilling for new seawall.
Chicago Park District contractors install sheet pilling for new seawall.
Chicago Park District contractors install an anchoring wall along the south perimeter of DuSable Park.
Chicago Park District contractors install an anchoring wall along the south perimeter of DuSable Park.