This is not the current EPA website. To navigate to the current EPA website, please go to www.epa.gov. This website is historical material reflecting the EPA website as it existed on January 19, 2021. This website is no longer updated and links to external websites and some internal pages may not work. More information »

New Source Review (NSR) Permitting

NorthStar Bluescope Steel, LLC - Permitting Information

1. Facility Information

NorthStar Bluescope Steel, LLC

2. Location

6767 County Road 9
Delta, Ohio 43515
Fulton County
 

3. Distance from US/Canada Border

Approximately 86 km (in Lake Erie)
Approximately 94 km (Amherstburg, Ontario)
 

4. Facility Type and Size

Electric Arc Furnace Steel Mill, future total capacity of 4,070,000 tons of steel per year

5. Sources of Emissions

Modification involving expansion to mini mill operations resulting in increased facility production capacity. Expansion will include modification of existing operations and installation of the following new units: Electric Arc Furnace (EAF), twin-station Ladle Metallurgy Facility (LMF), casting operations, and support systems including cooling towers, natural gas fired ladles/tundish heaters & dryers, tunnel furnace, dust handling system, storage silos, limestone receiving, scrap handling/storage, & alloy handling/storage.

6. Type of Fuel

Natural gas is used for the heaters, boilers, tunnel furnace, and preheat of the EAF.

7. Type and Quantity of Emissions

Pollutant Tons/yr

CO

11,579

NOx

1,052

PM10

313

PM2.5

295

SO2

577

VOC

726

8. Emission Control Technology

Electric Arc Furnace
Baghouse control system consisting of:
  1. direct evacuation control (DEC) system for collection of emissions from P905 and P906
  2. roof canopy hood system for collection of emissions fugitive to the inside of Meltshop #2 from casting operations (P907-Caster #2) and emissions not captured by the DEC control systems
  3.  DEC control systems (P905 and P906) and canopy hood collection system shall be vented to a baghouse achieving the following maximum outlet concentrations:
  4. 0.0018 gr/dscf for PE;
  5. 0.0024 gr/dscf for PM10/PM2.5
North Alloy Storage and Handling
Use of a fabric filter with a maximum outlet concentration of 0.0024 gr PE/PM10/PM2.5 per dscf
 
Tunnel Furnaces
Use of natural gas, good combustion practices and design resulting in an emissions rate of 1.12 lbs PE/PM10/PM2.5 per hr, and compliance with the emission standard of 0.01 lb PE/PM10/PM2.5 per mmBtu heat input
 
Cooling Towers
Use of drift eliminator(s) designed to achieve a 0.001% drift rate and maintenance of the total dissolved solids (TDS) content for each cooling tower
 
Lime & Carbon Silos
Use of a fabric filter with a maximum outlet concentration of 0.02 gr PE/PM10/PM2.5 per dscf
 
Ladle Dryers
Use of natural gas, good combustion practices and design resulting in an emissions rate of 0.05 lb PE/PM10/PM2.5 per hr, and compliance with the emission standard of 0.003 lb PE/PM10/PM2.5 per mmBtu heat input
 

9. Date Permit Application Received

The initial application 4/30/2019 and significantly revised applications were submitted on 5/14/2019 and 7/8/2019.

10. Stack Height and Diameter

DEC System
stack height: 70 ft
inside diameter: 20 ft
 

11. Permit Agency Contact

Mike Hopkins, P.E.
Assistant Chief, Permitting Section, DAPC
Ohio Environmental Protection Agency
Lazarus Government Center
50 West Town Street, Suite 700
P.O. Box 1049
Columbus, OH 43216
(614) 644-3611