An official website of the United States government.

This is not the current EPA website. To navigate to the current EPA website, please go to www.epa.gov. This website is historical material reflecting the EPA website as it existed on January 19, 2021. This website is no longer updated and links to external websites and some internal pages may not work. More information »

Office of Inspector General

Report: Lack of Project Plan Resulted in Transition and Contractor Performance Problems for the Institutional Controls Tracking System

Report #09-P-0128March 25, 2009

What Was Found

Lack of compliance with established project management procedures resulted in transitional problems in 2005 that delayed ICTS development and negatively affected contractor performance.

Report Materials

You may need a PDF reader to view some of the files on this page. See EPA’s About PDF page to learn more.