This is not the current EPA website. To navigate to the current EPA website, please go to www.epa.gov. This website is historical material reflecting the EPA website as it existed on January 19, 2021. This website is no longer updated and links to external websites and some internal pages may not work. More information »

PE certifying a technical amendment

Except as provided in 40 CFR §112.6 for qualified facilities, a Professional Engineer (PE) must certify all technical amendments to an existing SPCC Plan (§112.5(c)).  When certifying a technical change to an existing SPCC Plan, does the PE have to inspect and certify the entire Plan or only the amended portion of the Plan?

The PE must only inspect and certify the portion of the Plan that has been technically amended, rather than the entire Plan.  Since the certifying PE may not have been involved in certifying the Plan originally, the PE’s certification and attestation only applies to that particular technical amendment.