This is not the current EPA website. To navigate to the current EPA website, please go to www.epa.gov. This website is historical material reflecting the EPA website as it existed on January 19, 2021. This website is no longer updated and links to external websites and some internal pages may not work. More information »

Is a PE required to review an SPCC Plan if it has not changed?

Under the 2002 regulations, is a PE required to review the SPCC Plans at the end of a 5-year SPCC Plan cycle if no changes have occurred at the facilities?

No.  It is the responsibility of the owner or operator to document the completion of a review and decide whether changes have occurred that would require a technical plan amendment and therefore a PE certification.