This is not the current EPA website. To navigate to the current EPA website, please go to www.epa.gov. This website is historical material reflecting the EPA website as it existed on January 19, 2021. This website is no longer updated and links to external websites and some internal pages may not work. More information »

SPCC Compliance Dates

What are the compliance dates for SPCC facilities?

A facility, including a mobile or portable facility, starting operation... Must...

On or before August 16, 2002

Maintain its existing SPCC Plan
Amend and implement the amended SPCC Plan no later than November 10, 2011

After August 16, 2002 through November 10, 2011

Prepare and implement an SPCC Plan no later than November 10, 2011

After November 10, 2011 (excluding production facilities)

Prepare and implement an SPCC Plan before beginning operations

After November 10, 2011 (production facilities) Prepare and implement an SPCC Plan within six months after beginning operations.*

*Note: EPA recognizes that for some oil fields, based on the often variable conditions of the oil reservoir, the type and proportion of products may be uncertain until after the process of extraction has started. On December 5, 2008 (73 FR 74236), EPA finalized an amendment to allow a new oil production facility (i.e., one that becomes operational after the compliance date).

What are the compliance dates for SPCC facilities that are offshore or that require a Facility Response Plan?

A drilling, production or workover facility, including a mobile or portable facility, located offshore or with an offshore component; or an onshore facility that is required to have and submit FRPs starting operation... Must...

On or before August 16, 2002

Maintain its existing SPCC Plan
Amend and implement the amended SPCC Plan no later than November 10, 2010

After August 16, 2002 through November 10, 2010

Prepare and implement an SPCC Plan no later than November 10, 2010

After November 10, 2010 (excluding production facilities)

Prepare and implement an SPCC Plan before beginning operations

After November 10, 2010 (production facilities) Prepare and implement an SPCC Plan within six months after beginning operations.

Regulation: Oil Pollution Prevention; Spill Prevention, Control, and Countermeasure Rule - Compliance Date Amendment (7 pp, 156 K, About PDF)

Top of Page

Compliance Date for Farms

May 10, 2013, is the compliance date for farms to prepare or amend and implement their Spill Prevention, Control, and Countermeasure (SPCC) Plans.

Fact Sheet: SPCC Compliance Date Extension for Farms

Top of Page

History

On July 17, 2002, EPA published a final rule that amended the SPCC regulations (67 FR 47042)(111 pp, 673 K, About PDF), which became effective on August 16, 2002. The final rule included compliance dates in §112.3 for preparing, amending, and implementing SPCC Plans. The original compliance dates were amended on:

These extensions provided additional time for:

  • the regulated community to understand the previous SPCC rule amendments in 2002 and 2009,
  • the clarifications developed by EPA during the course of litigation settlement proceedings (69 FR 29728)(3 pp, 184 K, About PDF),
  • and alleviated the need for individual extension requests.

Top of Page