This is not the current EPA website. To navigate to the current EPA website, please go to www.epa.gov. This website is historical material reflecting the EPA website as it existed on January 19, 2021. This website is no longer updated and links to external websites and some internal pages may not work. More information »

B622 PRIA Fee Category

PRIA 4 Fee Determination Decision Tree:

Biopesticide Biochemical/Microbial Experimental Use Permit


Below is the fee for your selected Fee Category for Fiscal Years 2020-2021

Action Code Description FY'20-FY'21 Fee Decision Time (months)
B622 Amendment; Experimental Use Permit; petition to amend an established or temporary tolerance or tolerance exemption.(3) $13,403 11

Do you plan to request either of the following types of waivers?

Waiver Pay Amount
50% waiver You pay ---->>>>> $6,702
75% waiver You pay ---->>>>> $3,351

To pay the fee shown above, go to Paying PRIA Application Fees web page and follow the instructions.

How to submit your application directly to EPA.

Action Code Interpretation

An application to amend an existing Experimental Use Permit for a microbial or biochemical pesticide. This use requires a change/amendment to the existing tolerance/temporary tolerance or exemption for any U. S. registered active ingredient that currently has an approved tolerance/temporary tolerance or exemption for the proposed use.

The Agency will provide the applicant with a pre-decisional determination 2 weeks prior to the PRIA decision review time due date which specifies any label changes that have to be made in order to grant the requested amendment. If the label issues cannot be resolved prior to the PRIA decision review time due date and if a PRIA due date time extension has not been agreed upon, then the Agency will issue to the applicant its regulatory decision with the specific label changes and supporting documentation on or just before the PRIA review time due date.

At that time the applicant must either (a) agree to all of the label changes and submit a revised label that incorporates all of these label changes; or (b) does not agree with one or more of the label changes and request up to 30 days to reach agreement with the Agency and submit a revised label that incorporates all of the agreed upon label changes, which the Agency has 2 business days to review; or (c) withdraw the application without prejudice.