This is not the current EPA website. To navigate to the current EPA website, please go to www.epa.gov. This website is historical material reflecting the EPA website as it existed on January 19, 2021. This website is no longer updated and links to external websites and some internal pages may not work. More information »

Compliance date for adding covered processes

What happens if I bring a new covered process on line (e.g., install a second storage tank) after submitting my original RMP?

For a new covered process added after the initial compliance date, you must be in compliance on the date you first have a regulated substance above the threshold quantity.  There is no grace period.  You must develop and implement all the applicable rule elements and update your RMP before your process contains more than a threshold quantity of a regulated substance.