This is not the current EPA website. To navigate to the current EPA website, please go to www.epa.gov. This website is historical material reflecting the EPA website as it existed on January 19, 2021. This website is no longer updated and links to external websites and some internal pages may not work. More information »

When were RMPs initially required to be submitted?

When must the risk management plans (RMPs) required under 40 CFR Part 68, Subpart G, initially be submitted?

For chemicals currently listed as regulated substances at 40 CFR §68.130, compliance with the risk management program requirements (including submission of RMPs) is required by June 21, 1999, or the date on which a regulated substance first becomes present above a threshold quantity in a process, whichever is later (40 CFR §68.10(a)). For substances subsequently added to the list, the due date for RMP submission will be three years after the date on which the regulated substance is first listed (40 CFR §68.10(a)(2)).