Regulatory Text:
Oklahoma Administrative Code, Title 252, Department of Environmental Quality
Chapter 4 (OAC 252:4). Rules of Practice and Procedure
Chapter 4, Appendix C, Permitting Process Summary
As adopted in the Oklahoma Register June 1, 2001 (18 Ok Reg 1922) effective June 11, 2001.
Submitted to EPA February 14, 2002, Regulations.gov document EPA-R06-OAR-2006-0389-0005 [OK005.05] and Regulations.gov document EPA-R06-OAR-2007-0989-0007 [OK007.07].
As approved by EPA May 15, 2017 (82 FR 22281) SIP effective June 14, 2017 (OKd21),
Regulations.gov document EPA-R06-OAR-2007-0989-0020 [OK007.20].
Explanation: "Applicable to minor NSR permitting under OAC 252:100-7. Approved for major NSR permitting 11/26/2010, 75 FR 72695. NOT in SIP: Tier I column."
(Appendix C is not cited in Chapter 4.)
Steps |
Tier I
|
Tier II
|
Tier III
|
---|---|---|---|
Filing - Applicant files application, pays any required fee, and provides landowner notice. Applicant may meet with the DEQ staff prior to this. |
Yes
|
Yes
|
Yes
|
Notice of filing - Applicant publishes notice in one newspaper local to site. |
No
|
Yes
|
Yes
|
Process meeting - Notice - 30-day opportunity is published with notice of filing. DEQ holds meeting if requested and sufficient interest is shown. |
No
|
No
|
Yes
|
Administrative completeness review - DEQ reviews application and asks applicant to supply any missing information. |
Yes
|
Yes
|
Yes
|
Technical review - DEQ reviews application for technical compliance and requests applicant to cure any deficiencies. |
Yes
|
Yes
|
Yes
|
Draft permit or draft denial - DEQ prepares this after completing review. |
No
|
Yes
|
Yes
|
Notice of draft permit, public comment period and public meeting request opportunity - Applicant publishes this in one newspaper local to site. (DEQ publishes notice of draft denial.) |
No
|
Yes
|
Yes
|
Public comment period - 45 days for hazardous waste treatment, storage or disposal draft permits; 30 days for all others. |
No
|
Yes
|
Yes
|
Public meeting - Conducted by DEQ if held |
No
|
Yes
|
Yes
|
Review of comments - DEQ (written response) |
No
|
Yes
|
Yes
|
Proposed permit - DEQ prepares this in response to comments on draft permit |
No
|
No
|
Yes
|
Notice of proposed permit - Applicant publishes, in one newspaper local to site, notice of 20-day opportunity to review permit and request administrative hearing. |
No
|
No
|
Yes
|
Administrative permit hearing - Conducted by DEQ if held. Results in final order. |
No
|
No
|
Yes
|
Issuance or denial - DEQ's final decision |
Yes
|
Yes
|
Yes
|
** end OK Chapter 4, Appendix C, Permitting Process Summary, SIP effective June 14, 2017 (OKd21) **