This is not the current EPA website. To navigate to the current EPA website, please go to www.epa.gov. This website is historical material reflecting the EPA website as it existed on January 19, 2021. This website is no longer updated and links to external websites and some internal pages may not work. More information »

Oklahoma SIP: OK Regulation 1.4.3: Operating Permit, SIP effective 1983-08-25 (OKc26), Effective 2010-12-27 (OKd07) to 2017-06-13

OK Regulation 1.4.3 Operating Permit; SIP effective 1983-08-25 (OKc26). Effective 2010-12-27 (OKd07) to 2017-06-13 for Minor sources only -- NOT IN SIP effective 2017-06-14 (OKd21)

Regulatory Text:
1.4.3  Operating Permit

Approved by EPA 08/25/1983 (48 FR 38636) at 52.1920(c)(26) effective 08/25/1983.
Effective December 27, 2010, Regulation 1.4.3 is for Minor sources only. See 75 FR 72695 (November 26, 2010)(OKd07) OK006
Regulations.gov docket EPA-R06-OAR-2007-0314

Outline:
1.4.3  (a)  Requirements
1.4.3  (b)  Permit Applications
1.4.3  (c)  Operating Permit Conditions


1.4.3  (a)  Requirements
            (1)  No person shall cause or permit the operation of a new source for more than a 60-day period without applying for a permit to operate from the Commissioner.
            (2)  No owner or operator shall cause or permit the operation of a new source if the Commissioner denies or revokes a permit to operate.

1.4.3  (b)  Permit Applications
            (1)  Application will be made on a form provided by the Commissioner.  The supplementary data required with this form is:
                 (A)  The start-up date, or phased dates when applicable.
                 (B)  Revisions to the installation/ construction, if any, that differed from the construction design and plan given in the permit application material, data and specifications.
            (2)  Before a permit to operate a new source is granted, the applicant, if required by the Commissioner, shall conduct emission tests in accordance with methods approved by the Commissioner with the tests being made at the expense of the applicant.  The Commissioner may monitor performance tests conducted by the applicant and may also conduct emissions tests.  Further, the results of any required test must be provided to the Commissioner along with supporting information as required.

1.4.3  (c)  Operating Permit Conditions.
            (1)  Emissions limitations established and made a part of the construction permit are carried over, incorporated into and are enforceable limitations of the subsequently issued operating permit.