This is not the current EPA website. To navigate to the current EPA website, please go to www.epa.gov. This website is historical material reflecting the EPA website as it existed on January 19, 2021. This website is no longer updated and links to external websites and some internal pages may not work. More information »

Texas 30 TAC Chapter 55, Subchapter E, Section 55.152, Public Comment Period, SIP effective June 8, 2018 (TXd206) to August 11, 2019

Regulatory Text:

Texas Commission on Environmental Quality

55 Chapter 55 – Request for Reconsideration and Contested Case Hearings: Public Comment

55E SUBCHAPTER E : PUBLIC COMMENT AND PUBLIC MEETINGS

55E Section 55.152. Public Comment Period.
As approved by EPA May 9, 2018 (83 FR 21178), SIP effective June 8, 2018 (TXd206).
SIP includes 55.152(a)(1), (a)(2), (a)(3), (a)(6), (a)(7), and (b),
as adopted by TCEQ December 7, 2016 effective December 29, 2016 (55-I),
submitted to EPA February 21, 2017 (TX-403),
Regulations.gov document EPA-R06-OAR-2017-0124-0007 [TX198.07].
Approved by EPA May 9, 2018 (83 FR 21178), SIP effective June 8, 2018 (TXd206),
Regulations.gov docket EPA-R06-OAR-2017-0124 [TX198],
Explanation: SIP includes 55.152(a)(1), (a)(2), (a)(3), (a)(6), (a)(7), and (b).

§55.152. Public Comment Period.
   (a) Public comments must be filed with the chief clerk within the time period specified in the notice. The public comment period shall end 30 days after the last publication of the Notice of Application and Preliminary Decision, except that the time period shall end:
       (1) 30 days after the last publication of Notice of Receipt of Application and Intent to Obtain Permit under §39.418 of this title (relating to Notice of Receipt of Application and Intent to Obtain Permit), or 30 days after Notice of Application and Preliminary Decision if a second notice is required under §39.419 of this title (relating to Notice of Application and Preliminary Decision), for an air quality permit application not otherwise specified in this section;
       (2) 30 days after the last publication of the consolidated Notice of Receipt of Application and Intent to Obtain Permit and Notice of Application and Preliminary Decision under §39.603 of this title (relating to Newspaper Notice) for a registration for a concrete batch plant under the Air Quality Standard Permit for Concrete Batch Plants adopted by the commission under Chapter 116, Subchapter F of this title (relating to Standard Permits), unless the plant is to be temporarily located in or contiguous to the right-of-way of a public works project;
       (3) 15 days after the last publication of Notice of Receipt of Application and Intent to Obtain Permit under §39.418 of this title, or 30 days after Notice of Application and Preliminary Decision if a second notice is required under §39.419 of this title, for a permit renewal under Chapter 116 of this title (relating to Control of Air Pollution by Permits for New Construction or Modification);
       (4) NOT IN SIP
       (5) NOT IN SIP
       (6) the time specified in commission rules for other specific types of applications; or
       (7) as extended by the executive director for good cause.
   (b) The public comment period shall automatically be extended to the close of any public meeting.