This is not the current EPA website. To navigate to the current EPA website, please go to www.epa.gov. This website is historical material reflecting the EPA website as it existed on January 19, 2021. This website is no longer updated and links to external websites and some internal pages may not work. More information »

Verified Technologies for SmartWay and Clean Diesel

Testing for SmartWay Verification of Idling Reduction Technologies (IRTs) for Trucks

Follow these steps for the testing part of the verification process:

Number One Develop a test plan for EPA approval.

  • Choose a test facility for the chosen test method;
  • EPA will provide a draft IRT test protocol and assist in test plan development; and
  • Finalize test plan for EPA approval.

Number Two Conduct testing.

  • The device manufacturer is responsible for:
  • Ensuring that testing is conducted in accordance with EPA SmartWay protocols;
  • Immediately reporting any issues to EPA.

If necessary, EPA may observe some or all of the testing.

""Compile and submit a test report to EPA.

Once testing is complete, the manufacturer must work with the testing facility to submit a report that includes the following:

  • Description of the test facility and test protocol;
  • Photos of test vehicles and devices tested;
  • Name(s) of device(s) tested; and
  • All applicable data and descriptions of analyses.

For further guidance, see Appendix A in: Draft Test Protocol for Truck IRTs

"" Go to the Evaluation phase.

Once all data, test reports, and associated documents are submitted to EPA, the device will be evaluated in the final phase of verification.