This is not the current EPA website. To navigate to the current EPA website, please go to www.epa.gov. This website is historical material reflecting the EPA website as it existed on January 19, 2021. This website is no longer updated and links to external websites and some internal pages may not work. More information »

Clean Air Markets

Acid Rain Program 1997 Applicability Determinations

View EPA's formal responses to written requests for applicability determinations under 40 CFR 72.6 from 1997.

You may need a PDF reader to view some of the files on this page. See EPA’s About PDF page to learn more.
  • Almond Power Plant (PDF)(2 pp, 13 K, October 27, 1997)
    A 49 MWe gas turbine engine that commenced commercial operation in April 1996. 40 CFR 72.6(b), 40 CFR 72.2 (definitions of "new unit" and "utility unit").
  • Grays Ferry (PDF)(3 pp, 19 K, August 18, 1997)
    Two cogeneration units whose construction commenced in August 1993. 40 CFR 72.6(b)(4)(ii), 40 CFR 72.6(b)(5) and (6), 40 CFR 72.2 (definitions of "unit," "cogeneration unit," "qualifying power purchase commitment," and "power purchase commitment").
  • South Boston Power Complex (PDF)(2 pp, 13 K, October 27, 1997)
    A simple combustion turbine that commenced commercial operation in 1979, but was later sold and moved to a different site. 40 CFR 72.6(b)(1).
  • Star Repowering Project (PDF)(5 pp, 26 K, August 14, 1997)
    An existing cogeneration unit constructed in the late 1950's and two new cogeneration units whose construction was projected to commence in mid-1997. 40 CFR 72.6(b)(4)(i), 40 CFR 72.6(b)(4)(ii), 40 CFR 72.6(a)(3)(iv), 40 CFR 72.2 (definitions of "unit" and "cogeneration unit").