Summary of Part 75 Administrative Processes: Table 6
Revised 3/11/2009
Submittal Requirement | Rule Citation(s) | Contents of Submittal | Submit to Whom? | Submit When? | Comments |
---|---|---|---|---|---|
Operation of new unit, newly affected unit, new stack or new FGD | § 75.61 (a)(2) | Notification of date of commencement of commercial operation of new or newly affected unit or planned date of initial use or operation of new stack or FGD. | CAMD, EPA Region, State. | ≥ 45 days prior to the applicable date. | If the planned date changes, submit notice of actual date ≤ 7 days after the actual date of initial operation or usage (as applicable). |
Unit shutdown and recommencement of commercial operation | § 75.61 (a)(3), § 75.4 (a) and (d) |
Notice of dates of unit shutdown and recommencement of commercial operation, for a unit relying on § 75.4 (d) to postpone certification testing. | CAMD, EPA Region, State. | For planned shutdown, ≥ 21 days prior to certification deadline in § 75.4 (a). For unplanned shutdown, provide notice ≤ 7 days following the shutdown. |
If actual date differs from planned date, submit notice of actual date ≤ 7 days following actual date of shutdown or recommencement of commercial operation (as applicable). |
Long Term Cold Storage (LTCS) | § 75.61 (a)(7) | Notice of placing a unit into LTCS, either to postpone initial certification under §75.4 (d) or to discontinue submittal of quarterly reports under §75.64 (a). | CAMD, EPA Region, State. | Unspecified. | EPA recommends that the notice be provided within 7 to 10 days of unit shutdown. |
Notice of expected date of unit restart | 45 days prior to the expected date of unit restart. | If actual date differs from expected date, submit notice of actual date ≤ 7 days following actual date of unit restart. | |||
Postponement of Appendix E Testing for Backup Fuel | § 75.61 (a)(4), § 75.4 (a) and (f) |
For an Appendix E unit relying on § 75.4 (f) to postpone testing on backup fuel, provide notice of that fact. | CAMD, EPA Region, State. | ≥ 45 days prior to certification deadline in § 75.4 (a). | ------------- |
Initial Combustion of Backup Fuel for which Appendix E Testing was Postponed | § 75.61 (a)(4), § 75.4 (a) and (f) |
After the certification deadline in § 75.4 (a), provide notice of combustion of any fuel for which Appendix E testing was not performed prior to the deadline. | CAMD, EPA Region, State. | No later than 7 days after first date of combustion of the fuel. | Notification must include either actual or projected date of Appendix E testing after initial combustion of the fuel. |
Notice of Combustion of Emergency Fuel (Appendix D or E) | § 75.61 (a)(6) | Provide notice of emergency fuel combustion. Indicate the exact date(s) and hour(s). | CAMD, EPA Region, State. | In the Comment field of the electronic quarterly report. | ------------ |