This is not the current EPA website. To navigate to the current EPA website, please go to www.epa.gov. This website is historical material reflecting the EPA website as it existed on January 19, 2021. This website is no longer updated and links to external websites and some internal pages may not work. More information »

Section 404 of the Clean Water Act

Dispute Resolution under CWA Section 404(q)

This page provides updates and background information regarding EPA actions taken pursuant to Clean Water Act Section 404(q). This section establishes a requirement that the Secretary of the Army and the Administrator of EPA enter into an agreement assuring that delays in the issuance of permits under Section 404 are minimized. In August 1992, Army and EPA released a Section 404(q) Memorandum of Agreement (MOA) that outlines the current process and time frames for resolving disputes, in an effort to issue timely permit decisions.

Pending Elevations

  • None

Section 404(q) Background Materials